BKV Operations Updates – Sendera Ranch

BKV plans to perform re-stimulation and well maintenance operations on several wells located in the Sendera Ranch neighborhood in north Fort Worth. At the end of April, our team began working to prepare the locations for the upcoming operations at our Morris Harmonson location. Re-stimulation of natural gas wells in the Barnett Shale is a standard best practice of our development plans. We leverage state-of-the-art technology to “re-stimulate” existing wells for increased production and maximum well efficiency. During this time, and always, safety is our top priority. Employees and contractors are held to a high standard and required to comply with all safety rules and regulations. In addition, we are closely adhering to the requirements provided by the City of Fort Worth Oil & Gas ordinance, as well as other local operations regulations, and are committed to partnering with the neighbors to ensure everyone’s safety.

We will update this site with information regarding current and upcoming re-stimulation projects in Sendera Ranch.

Morris Harmonson Project Timeline

 

May 9th - May 12th

Installation of sound walls

May 25th - May 27th

Re-Stimulation of Wells

 

June 10th - June 14th

Drill out rig on locations to bring wells back online

June 15th - June 17th

Removal of sound walls

 

All timelines are approximate and given as a reference only. Dates can shift due to changes in operational and environmental factors. We will continue to update this site accordingly.

Project Details

Below are specific details regarding BKV’s re-stimulation operations at the Morris Harmonson pad location north of Avondale Haslet Road (as soon on the map).

  • BKV’s increased activity is temporary and is planned to conclude early June.

  • Hours of operation will be limited to between the hours of 6 a.m. to 7 p.m. Monday - Saturday, and no operation hours on Sunday.

  • Temporary walls have been constructed on the wellsite location to reduce the sound coming from the location. These walls will be removed upon completion of this project.

  • All trucks will enter and depart this location from an existing BKV lease road to minimize the impact on local community traffic.

  • BKV has partnered with a local security company to monitor the location. An unarmed security guard will be on site from 6 pm – 6 am during re-stimulation (currently targeted for May 25 -27) to serve as a watchman and to ensure that only appropriate personnel have access to the area outside of normal operations hours.

  • At the conclusion of the project, normal day-to-day operations will resume.

Frequently Asked
Questions

 

Is this activity permanent?

No, the re-stimulation operations on these locations have already begun and are expected to last between 4 to 6 weeks. Safety will remain the top priority during this time, but we will move forward as efficiently as possible. However, as with all oil & gas operations, different operational and environmental factors can cause shifts in the project timeline.

Has this been approved by the city?

Yes. BKV is adhering to all requirements set forth from the City of Fort Worth and the State of Texas. I

Will the large walls be removed?

Yes, upon completion of the project, the walls will be deconstructed and safely removed.

Who is BKV?

BKV is a natural gas exploration and production company headquartered in Denver, Colorado, with a regional office located in Bridgeport, Texas. Learn more about us at bkvcorp.com. BKV acquired Devon Energy’s assets in the North Texas Barnett Shale in 2020.

Can I reach out to BKV directly to ask questions?

Yes. Please complete the contact form available at the bottom of the page with any questions or concerns, and we will respond promptly. You may also call us directly at either of the below phone numbers.

  • Landowner Relations: 1.833.258.5263

  • 24-Hour Emergency Contact: 1.833.425.8677 (emergencies only)